Skip to main content

Help Center

Create Task Dependencies

The project module supports dependencies within project tasks. Specifically, a user can employ both Start-to-Start dependencies and End-to-Start dependencies in their projects. Dependencies can be implemented across tasks and within sub-tasks of a parent task. To use this feature in one of your existing projects, follow the steps outlined below.

  • Navigate to one of your active projects.

  • Click on the ellipsis next to a task, and select Edit Task.

  • To implement an End-Start dependency, use the multi-select under “End-Start Predecessor” to select a task for this task to be dependent on. When you set a task to depend on the End of another task, the dependent task’s start and end dates will update.

    Note

    For example, my Build task is dependent on completing my Design task. My SOW Task is set to end on 4/14. When I make my Build task have an End-Start Predecessor of Design, the system will update the Build start date to 4/15.

  • The Start-to-Start Predecessor will update a dependents task to have the same date as the task it depends on.

    Note

    For example, now that Build is dependent toDesign and Builds start date updated to 4/15, you can make Launch depend on the start of Build by making a start-to-start dependency. The Launch start date will change to the same start date as Build.

  • You can also make sub-tasks dependent on each other, as long as they belong to the same parent task. However, you can’t create an End-to-Start dependency that will set a sub-task due date outside of the parent task date.